M2 Process

M2 validates install completion, monitoring access, permitting, NEM application, final inspection evidence, and any change-order finalization.

Milestone Timing

Field Detail
Begins When Installation is complete and the partner can provide post-install photos, monitoring access, and permitting/inspection evidence.
Ends When MAC approves the post-install package and the project can proceed toward PTO and M3.
Common Delay Monitoring access, final inspection evidence, or change-order design/BOM materials are incomplete.

Sequence of Events

  1. Install complete
    Partner uploads install-complete photos and commissioned-system evidence.

  2. Monitoring access granted
    Partner adds Monitoring@getmacfinance.com to solar and battery monitoring platforms.

  3. Permitting package reviewed
    Partner submits permitting, NEM application, and passed inspection evidence.

  4. M2 approval clears PTO path
    MAC approves the post-install package and the project moves toward PTO and M3.

Document Status Submitted By Abridged Notes
Install-Complete Photos Partner-submitted
Required
EPC
Complete project photo set.
Access to Monitoring Portal Partner-submitted
Required
EPC
Use Monitoring@getmacfinance.com.
Required
EPC
System registered and commissioned.
Design / Engineering Report Partner-submitted
Conditional
EPC
Final design if change order occurred.
Bill of Material (BOM) Partner-submitted
Conditional
EPC
Final BOM if change order occurred.
City / County Permitting External-generated
Required
AHJ / EPC
City/county permit evidence.
NEM Utility Application External-generated
Required
Utility / EPC
Utility NEM application.
Required
AHJ / EPC
Passed final building/electrical inspection.