M2 Process
M2 validates install completion, monitoring access, permitting, NEM application, final inspection evidence, and any change-order finalization.
Milestone Timing
| Field | Detail |
|---|---|
| Begins When | Installation is complete and the partner can provide post-install photos, monitoring access, and permitting/inspection evidence. |
| Ends When | MAC approves the post-install package and the project can proceed toward PTO and M3. |
| Common Delay | Monitoring access, final inspection evidence, or change-order design/BOM materials are incomplete. |
Sequence of Events
-
Install complete
Partner uploads install-complete photos and commissioned-system evidence. -
Monitoring access granted
Partner adds Monitoring@getmacfinance.com to solar and battery monitoring platforms. -
Permitting package reviewed
Partner submits permitting, NEM application, and passed inspection evidence. -
M2 approval clears PTO path
MAC approves the post-install package and the project moves toward PTO and M3.
Required Documents
Section titled “Required Documents” Document Status Submitted By Abridged Notes
System Registered & Commissioned Photo Partner-submitted
Required
EPC
System registered and commissioned.
Design / Engineering Report Partner-submitted
Conditional
EPC
Final design if change order occurred.
Passed Final Building & Electrical Inspection External-generated
Required
AHJ / EPC
Passed final building/electrical inspection.
Document Status Submitted By Abridged Notes
System Registered & Commissioned Photo Partner-submitted
Required
EPC
System registered and commissioned.
Design / Engineering Report Partner-submitted
Conditional
EPC
Final design if change order occurred.
Passed Final Building & Electrical Inspection External-generated
Required
AHJ / EPC
Passed final building/electrical inspection.