M1 Process

M1 locks the pre-install package, project payment structure, Supplier Direct Pay treatment, and M1 Approval / Work Order.

Milestone Timing

Field Detail
Begins When NTP has been approved and the partner is ready to submit survey, design, BOM, and pre-install materials.
Ends When MAC issues the M1 Approval / Work Order and the EPC countersigns it.
Common Delay Production or scope changes require updated PPA/proposal materials before M1 can be approved.

Sequence of Events

  1. NTP approval confirmed
    The NTP Approval Notice is treated as a prerequisite for M1.

  2. Design package submitted
    Partner submits site survey, design/engineering, BOM, and requested supporting reports.

  3. Change-order review
    Residential changes above 10% or commercial changes above 5% require updated PPA/proposal materials.

  4. M1 work order locked
    MAC issues the M1 Approval / Work Order and locks payment distribution and Supplier Direct Pay treatment.

Document Status Submitted By Abridged Notes
NTP Approval Notice MAC-generated
Prerequisite
MAC
Triggered by MAC after NTP approval.
Site Survey Report Partner-submitted
Required
EPC
Site conditions and field survey.
Design / Engineering Report Partner-submitted
Required
EPC
Design and engineering package.
Signed PPA Agreement MAC-authored
Conditional
EPC + Property Owner
Updated PPA if change order is required.
Copy of the Proposal Partner-submitted
Conditional
EPC
Updated proposal if change order is required.
Bill of Material (BOM) Partner-submitted
Required
EPC
Domestic Content and FEOC-compliant equipment list.
Property Appraisal External-generated
Conditional
Appraiser
Only if requested by MAC.
Environmental Report External-generated
Conditional
Environmental consultant
Only if requested by MAC.
Required
MAC issues; EPC countersigns
Issued by MAC and countersigned by EPC.